Projects
Our business continues to grow: we have introduced the Turbine Solutions business unit, which has undertaken major projects in the UK with local and international partners.
ON-SHORE PROJECTS
Exxon Fife
Gas Turbine
MS5002 replacement
Baker Hughes
Year: 2021
Duration: 5 months
Total number of workforce: 25
Iggesund Paperboard
Workington
Steam Turbine and
Generator Major inspections
Baker Hughes
Year: 2021/2022
Duration: 10 months
Total number of workforce: 12
SHELL St. Fergus
Liner and transition piece
inspection on GT Frame 5002
Baker Hughes
Year: 2021 and 2023
Duration: 1,5 months on both occasions
Total number of workforce: 20
INEOS Hull
Installation and commissioning of four steam turbines plus auxiliaries
Baker Hughes
Year: 2021
Duration: 7 months
Total number of workforce: 100
ConocoPhillips
Teeside
Gas turbine Frame 3 Major inspection
and Compressor minor inspection
Baker Hughes
Year: 2021 and 2023
Duration: 3 months
Total number of workforce: 5
Humber – Phillips 66
Gas turbine Frame 3
Major inspections
Baker Hughes
Year: 2022 and 2024
Duration: 2,5 months
Total number of workforce: 5
Iggesund Paperboard
Workington
Steam Turbine
and Generator Minor inspections
Baker Hughes
Year: 2023
Duration: 1,5 months
Total number of workforce: 5
Interconnector
Bacton
Gas Turbine LM2500 inspection
and upgrade
Baker Hughes
Year: 2024
Duration: 2 months
Total number of workforce: 10
SHELL St. Fergus
GT Frame 5002
modular replacement
Baker Hughes
Year: 2024
Duration: 2,5 months on both occasions
Total number of workforce: 23
OFF-SHORE PROJECTS
PTF Dana Triton
Installation of two compressors
and DGSs
Baker Hughes
Year: 2021
Duration: 1 months
Total number of workforce: 2
PTF Tiffany
Gas turbine PGT10
Major inspection
Baker Hughes
Year: 2021
Duration: 2 months
Total number of workforce: 2
PTF Ithaca
Reciprocating Compressor
4SHMB/3
Baker Hughes
Year: 2023
Duration: 1 months
Total number of workforce: 3
PTF Dana Triton
Gas Turbine LM6000
change out
Baker Hughes
Year: 2024
Duration: 1 months
Total number of workforce: 3
PTF Judy Joanne
Compressor thrust bearing
change out
Baker Hughes
Year: 2024
Duration: 1 months
Total number of workforce: 1